1. The critical path is the:
A Shortest path in the network
B Longest path in the network
C Path in which some activities contain floats
# D Path which has the maximum float
2. What items should be considered when selecting a supplier?
A Dependability
B Product quality
C Location
# D All of above
3. Project integration involves:
A Efficient use of network schedules
# B Effective coordination and control
C Making the responsibility matrix
D Meetings of all the stakeholders
4. The Project Management Plan is owned by the:
A Sponsor
B Customer
C Project manager
# D A and C
5. A project is a:
A Repetitive process
B Unique and temporary endeavour
C Has a definite beginning and end
# D B and C
6. A sequence of phases through which the project evolves is known as:
# A The Project Life Cycle
B Project Gates
C Milestone charts
D Project Management Plan
7. The Project Management Plan establishes the:
# A Why, what, how, and when of the project
B What, how, how much and when of the project
C Why, what, how, how much and when of the project
D Why, what, how and how much of the project
8. A good project manger does not have to be a good:
# A Technocrat
B Communicator
C Integrator
D Risk manager
9. Which of the following is necessary for a project manager?
# A The responsibility, authority and accountability for the project
B The responsibility and accountability for the project
C The responsibility through line management for the project
D The responsibility through the client-sponsor for the project
10. A project phase is:
A An endeavor of considerable scope encompassing a number of projects
B A sub project
C The state of the project at a given time
D Marked by completion of one or more deliverable
11. The Business case should include:
A Criteria to judge whether the project is a success or failure
B Why the project is required
C The major project risks
# D All of the above
12. _____________defines why the project is required and what the project will do:
A Project Management Plan
B Project Charter
C Marketing & Sales
# D Business Case
13. Project life cycle phases are used to:
A Avoid the need for a project manager
B Lessen the conflict in project teams
# C Ensure that resources are not wasted
D Better define the Business case
14. Which of the following is not true about analogous estimating technique?
A Estimate is based on past projects.
B It is not very accurate.
# C It uses bottom-up approach
D It is a form of an expert judgment
15. An “S” curve:
A Shows cumulative values
B Describes allocation of resources
# C An output of cost estimating
D Shows interrelationships between projects
16. A Work Breakdown Structure:
A Is a key tool used in project management
B Forms the basis for planning the project, networks and bar chart
C Criteria used for calculating Earned Value is determined from the WBS
# D All of the above
17. The project is likely to be delayed if:
# A There are too many changes
B If proper planning is carried out in the beginning
C There is a no shortage of cash
D There are no quality assurance functions
18. “I cannot test the software until I code the software”. This expression describes which of the following dependencies?
A Discretionary
B Soft
# C Mandatory or hard
D Regulated
19. On large projects, detailed documentation:
A Should be avoided to the extent possible since it adds to bureaucracy and project costs
B Has costs that typically lie in the 10%-15% range
# C Is needed to keep track of what is happening
D A and B
20. The Project Management Plan should be formally accepted by the:
A Project Manager
B Project Manager, Sponsor and project team
C Project Manager and Sponsor
# D Customer
0 Comments: