1. Scope management plan is necessary:
A For small projects only
B For all kind of projects
C For complex projects
D For R& D projects only
2. Increasing the level of the WBS from 3rd to 4th level will result in:
A Extra efforts to be spent with less return
B Being part of the fashion to go in more depth
C Better control of the project
D More headaches in reporting progress
3. Work not included in the WBS is:
A To be detailed out later
B Outside the scope of the project
C Will be taken care of at the time of executing the project
D Needs management attention
4. Select three features found in the WBS from the list below:
1 A graphical display of the total project work
2 Work to be included in the WBS is decided as the project moves along
3 Is required only for large projects
4 Shows the hierarchy of the persons involved in the project
5 the total quantum of project work broken down into smaller groups of activities
6 Is detailed top-down
7 Is detailed bottom-up
5. The work breakdown structure is an excellent tool for detailing the work content of a project. However, which of the following will not be gained through the WBS:
A Assessing the quality of the work performed
B Assessing the risk impact
C Assessing the time estimates
D Assessing the cost estimates
6. When do you think the WBS should first be created?
A During scope changes in a project
B During the feasibility study
C When the project is being executed
D At beginning of a project in the planning phase
7. A project network is a graphical display showing ……………………….:
A arrows and nodes
B sequence of project activities
C activities
D resources used in the project
8. The network is used by the project manager to:
A Identify relationship between tasks
B Optimize the usage of resources
C Develop the project schedule
D All of the above
9. Two techniques used for drawing project networks are known as:
A Activity and Arrow drawing methods
B Arrow and circle drawing methods
C ADMs and PDMs
D ADMs and ADCs
10. The person drawing the network must to be clear about:
A The project's goals and objectives
B The duration of each activity
C The logical sequence of activities
D All of the above
0 Comments:
Post a Comment