1. Projects can be classified by:
A The industry they fall in
B The total cost of the project
C The size of the project
D All of the above
2. Some key characteristics of a project are:
A Temporary, unique, have fixed goals and can use unlimited resources
B Temporary, unique, have pre-defined goals and follow phases
C Temporary, unique, have fixed goals and face limited risks
D Temporary, unique, face risks and have unlimited budgets
3. A project faces risks because:
A There are some known problems that could come up
B An unknown problem can jeopardize the project
C There are many uncertainties
D All of the above
4. The objectives of projects and operations:
A May be same
B Depends on the project involved
C Are totally different
D Depends on the organization
5. Operations is used for:
A The handing over of the project
B Repetitive work
C A concerted one time effort
D None of the above
6. Both operations and projects should be _____________ .
A Well executed to succeed
B Planned, executed and controlled
C Fully controlled to achieve success
D Extremely well planned to achieve success
7. What is not a feature of the business case?
A It is developed from the need statement
B It describes the 'why' of the project and the preferred solution
C It doesn't contain details of the investment appraisal
D It forms the basis for authorizing the project
8. What is not a role of the project sponsor?
A Guiding the project at a strategic level according to the organizational needs
B Managing the project
C Accept the project at its completion
D Authorizing the project to proceed to the next phase
9. Double declining balance is a form of:
A Decelerated depreciation
B Straight line depreciation
C Accelerated depreciation
D Life cycle costing
10. You are appraising three projects. The NPV of Project A is $10000, NPV of Project B is -$10000 and the NPV of Project C is $12000. Which project would you select?
A Project A
B Project C
C Project B
D Not enough information is given
0 Comments:
Post a Comment