MPM 004 - Project Closeout (PGCPM Questions and Answers - 2)

21.  Assemble product components is an

 A  Infinity process

 B  Incremental process

 C  Identical process

 D  Undefined process

 

22.  Before assembling any product component one should ensure:

 A  Readiness of product integration environment

 B  Each component should be confirmed to be compliant with its interface requirement.

 C  Integration sequence is properly defined and reviewed.

 D  All of the above

23.  Product evaluation can be done at two levels:

 A  Planning and organizing

 B  Verification and validation

 C  Quality control and quality assurance

 D  Sequencing and assembling

 

24. Verification of product can be done by

 A  Structured walkthroughs.

 B  Demonstration of functionality

 C  Planned inspection meetings.

 D  A & C

 

25.  Document management does not include:

 A  Document development

 B  Document control

 C  Document review

 D  Document approval

 

26.  Project initial document is not:

 A  Project quality plan

 B  Project management plan

 C  Project charter

 D  Project scope statement

 

27.  Priority Setting techniques are:

 A  Compromise and consensus

 B  Top down and rolling wave

 C  Dot Voting and Weighted voting

 D  Probability and Impact

 

28.  Most appropriate technique use for group priority setting is

 A  Dot Voting

 B  Weighted Voting

 C  Consensus Decision

 D  Multi Voting

 

29.  Parato analysis helps to identify

 A  About 20% of the most critical issue

 B  About 80% of the most critical issue

 C  About 100% of the issue status

 D  About 20% of the issue status.

 

30.  Issue Histogram helps to

 A  Review all pending issues

 B  Give overall status of the project issues

 C  Identify the most critical issue in the project

 D  All of the above

 

31.  In carrying out effective contract administration, it is necessary to:

 A  Document all change requests

 B  Have a good contract change control system

 C  Have buyers and sellers develop a good personal relationship

 D  A and B

 

32.  The amount of monitoring of contractor's work by the project manager will vary based on:

 A  The value of the contract

 B  The type of contract being used

 C  The reputation of the contractor

 D  The nature of the work being done

 

 33.  What is NOT true?

 A  Both the buyer's and seller's project manager's should be aware of the contract's legal implications

 B  Seller must meet all contractual obligations

 C  Contractor must complete work receiving any payment

 D  Project manager is responsible to ensure seller is meeting all requirements

 

34.  Who issues the warranty?

 A  Manufacturer

 B  Customer

 C  Retailer

 D  A & C

 

35.  When is the warranty rights enforced against suppliers?

 A  When warranty is not violated

 B  When warranty is violated

 C  During pre-delivery of goods and services

 D  Suppliers do not meet the commitment in delivery

 

36.  In contract close out, one should:

 A  Measure the performance of a contracting organization based on specifications and the technical aspects

 B  Measure how well did the contractor behaved

 C  Measure the personal relationship with the contractor

 D  Measure customer satisfaction

 

37. During contract closeout a Product verification is done to:

 A  Ensure that the seller's work is complete and satisfactorily meets all the contract requirements

 B  Verify the product's design

 C  To document the seller's work

 D  Verify the work completed for making seller payments

 

38.  Contract Closeout involves all of the following except:

 A  Relocating the team members

 B  Formal acceptance of the work by the buyer

 C  Updating the contract file

 D  Product verification

 

39.  Contract closure should be done:

 A  If there is enough time

 B  If a contract is terminated before completion

 C  At the end of the contract

 D  B and C

 

40.  Who issues the purchase order?

 A  Buyer

 B  Seller

 C  Project Manager

 D  None of the above

 