1.  Which is the closest statement defining project start-up?

 A  When the project manager gets the team together to celebrate the start of the project

 B  When the CEO gives the project manager clearance to start the project

 C  It is characterized by great uncertainty and considerable time pressures

 D  It is the initial phase of the project life cycle

 

2.  Planning for the project is done in order to:

 A  Decide the work that needs to be done

 B  Plan the scope of the project

 C  Plan the time, scope and cost of the project

 D  Understand what we need to do and plan how to do the work

 

3.  Which of the following is not a subsidiary plan of the project management plan?

A  Risk Plan

B  Quality Control plan

C  Project plan

D  Staffing plan

 

4.  The Project Management Plan:

 A  Should be avoided for small projects as takes too much time

 B  Provides communication regarding the project to all the stakeholders

 C  Is like a Statement of Work

 D  None of the above

 

5.  The Project Management Plan is one of the most important documents in the project as it is:

 A  Used to execute the project

 B  Used to monitor and control the project

 C  Uses the outputs of other planning processes

 D  All of the above

 

6.  In the Project Management Plan, the -------------- and -------------- are management’s statement of the project’s success criteria:

 A  Why, what

 B  Why and How

 C  How, How much

 D  Why, when

 

7.  The Project Management Plan should be approved by the:

 A  CEO

 B  Client

 C  Sponsor

 D  Both Sponsor and the Project manager

 

8.  A plan is necessary to:

 A  Organize the work

 B  Define the scope of work

 C  Mobilize resources

 D  All of the above

 

9.  It is desirable to define and discuss the project's success criteria during which phase of the project life cycle?

 A  Before the conceptualization phase of the project

 B  During the conceptualization phase of the project

 C  In the implementation phase of the project

 D  Throughout the project

 

10.  The success criteria:

 A  Is the same for all the stakeholders

 B  Defines the qualitative and quantitative measures to judge the project’s success

 C  Is decided by the project manager

 D  Is always measured in terms of cost

 