1. Which is the closest statement defining project start-up?
A When the project manager gets the team together to celebrate the start of the project
B When the CEO gives the project manager clearance to start the project
C It is characterized by great uncertainty and considerable time pressures
D It is the initial phase of the project life cycle
2. Planning for the project is done in order to:
A Decide the work that needs to be done
B Plan the scope of the project
C Plan the time, scope and cost of the project
D Understand what we need to do and plan how to do the work
3. Which of the following is not a subsidiary plan of the project management plan?
A Risk Plan
B Quality Control plan
C Project plan
D Staffing plan
4. The Project Management Plan:
A Should be avoided for small projects as takes too much time
B Provides communication regarding the project to all the stakeholders
C Is like a Statement of Work
D None of the above
5. The Project Management Plan is one of the most important documents in the project as it is:
A Used to execute the project
B Used to monitor and control the project
C Uses the outputs of other planning processes
D All of the above
6. In the Project Management Plan, the -------------- and -------------- are management’s statement of the project’s success criteria:
A Why, what
B Why and How
C How, How much
D Why, when
7. The Project Management Plan should be approved by the:
A CEO
B Client
C Sponsor
D Both Sponsor and the Project manager
8. A plan is necessary to:
A Organize the work
B Define the scope of work
C Mobilize resources
D All of the above
9. It is desirable to define and discuss the project's success criteria during which phase of the project life cycle?
A Before the conceptualization phase of the project
B During the conceptualization phase of the project
C In the implementation phase of the project
D Throughout the project
10. The success criteria:
A Is the same for all the stakeholders
B Defines the qualitative and quantitative measures to judge the project’s success
C Is decided by the project manager
D Is always measured in terms of cost